Participants of should include the project manager, key project team members, and key representatives of the customer's organisation who were involved with the project.
A) a post-project evaluation meeting with the customer or sponsor
B) a project progress meeting with project stakeholders
C) an analysis session with the project team
D) a pre-RFP meeting with the customer
Correct Answer: