Risks Are Prioritised Based on

Question 31

Multiple Choice

Risks are prioritised based on


A) the likelihood of occurrence and degree of impact.
B) the order they are identified.
C) the gut feeling of the project team.
D) the priorities set in a different project.

Correct Answer: