Multiple Choice
involves the following: analysing cost performance to determine which work packages may require corrective action; deciding what specific corrective action should be taken; and revising the project plan, including time and cost estimates, to incorporate the planned corrective action.
A) Resource analysis
B) CPI monitoring
C) Cost control
D) Problem solving
Correct Answer:

Verified
Correct Answer:
Verified