Multiple Choice
Positive slack indicates the maximum amount of time
A) that the activities on the critical path should be accelerated to complete the project by the required completion time.
B) that each of the activities in the project can be delayed without jeopardising completion of the project by the required completion time.
C) that the activities with the positive slack should be accelerated to complete the project by the required completion time.
D) that the activities on a particular path can be delayed without jeopardising completion of the project by the required completion time.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: It is a good practice to have
Q6: Total slack is sometimes called<br>A)drift.<br>B)ride.<br>C)float.<br>D)sink.
Q10: Throughout the performance of the project, some
Q34: The total completion time is 25 days.Task
Q55: As the project progresses, the actual finish
Q56: The sponsor or customer often states the
Q79: Changes might be initiated by the customer
Q94: Negative slack indicates a lack of slack
Q99: Calculate the latest finish for Task B
Q105: Total slack for the project is the