Multiple Choice
The project control process must occur regularly throughout the project and include all of the following except
A) record information on changes to the project scope, schedule, and budget
B) gather data on actual performance.
C) having a single inspection of the project's deliverables at the end of the project.
D) establish regular reporting meetings to compare actual to planned progress.
Correct Answer:

Verified
Correct Answer:
Verified