Multiple Choice
If something is the statement of work, then it should be assumed that .
A) included; it will not change during the course of the project.
B) not included in; it will not be done or provided.
C) missing from; if the RFP stated the requirement it will be completed.
D) left out of; it will be completed during the project.
Correct Answer:

Verified
Correct Answer:
Verified