Multiple Choice
Acceptance criteria for all project deliverables must be than what is stated in the project charter or request for proposal.
A) repeated
B) described in greater detail
C) stated at higher levels
D) listed in sequence with the responsible person or organisation
Correct Answer:

Verified
Correct Answer:
Verified