Multiple Choice
While performing the work, all the activities in the baseline plan must be performed in accordance with
A) what the person responsible for the activity wants.
B) lessons learnt from prior projects.
C) how the sponsor has completed all their projects in the past.
D) the project schedule and technical specifications.
Correct Answer:

Verified
Correct Answer: