Multiple Choice
What has to be done to ensure that the weld has 100% penetration on thick plate or pipe?
A) The part must be preheated to above 350°F (175°C) before welding starts.
B) The welding machine needs to be set on its maximum amperage setting.
C) Make the molten weld pool as large as possible so it will melt all the way through.
D) The edges of the weld plate or pipe must have some type of groove made before welding.
Correct Answer:

Verified
Correct Answer:
Verified
Q5: What type of edge preparation for a
Q6: The _ is added to the basic
Q7: The strength value of a seam weld
Q8: For most welding processes, plates that are
Q9: Which of the following is true about
Q11: How might joint design influence welding cost?
Q12: Describe how the members of a tee
Q13: The faying surface can be shaped before
Q14: _ can ensure 100% joint fusion at
Q15: When the length of a seam weld