    The Formula to Calculate the Expected Time or the Weighted
Solved

The Formula to Calculate the Expected Time or the Weighted

Question 3

Question 3

Multiple Choice

The formula to calculate the expected time or the weighted average of the tasks, using the three time estimates for each task, is ________.


A) (a + 4m + b)
B) (a - 4m - b) /6
C) (a - 4m - b)
D) 6(a + 4m + b)
E) (a + 4m + b) /6

Correct Answer:

verifed

Verified

Related Questions

Q1: The formula used to calculate the payback

Q42: _ is accomplished by following a process

Q61: Business is transforming itself from a "command

Q68: _ is the stage at which the

Q74: List the steps to perform force-field analysis.

Q76: If a team is functional, individual participation

Q79: Describe the steps used to develop an

Q91: Differentiate between little s or big S

Q98: The scope of a process improvement team

Q99: The _ lists the major tasks involved

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines