Multiple Choice
A quality engineer notes that a process produces data that are binomial and has been obtained using a sample space that is constant. The primary interest of the process manager is in the percentage of bad parts. An appropriate control chart to use would be a(n) ________.
A) p chart
B) r chart
C) c chart
D) u chart
E) d chart
Correct Answer:

Verified
Correct Answer:
Verified