Multiple Choice
The marketing action plan (or launch plan) is:
A) a schedule of activities leading up to the event.
B) a schedule of meetings of the marketing management team, leading up to the event.
C) a schedule with a list of plans.
D) a list of expenses connected with the marketing.
Correct Answer:

Verified
Correct Answer:
Verified