Multiple Choice
It took James 1,400,000 yards at $2.50 per yard to make the 250,000 t-shirts.
-Refer to Figure 10-9. What is James' labor efficiency variance?
A) $800,000 U
B) $850,000 F
C) $800,000 F
D) $850,000 U
Correct Answer:

Verified
Correct Answer:
Verified