When Managers Investigate a Direct Labor Efficiency Variance, They Are

Question 57

Multiple Choice

When managers investigate a direct labor efficiency variance, they are trying to


A) place blame on the person responsible for the variance.
B) understand why workers took a longer or shorter amount of time than expected to produce a product.
C) find out which workers were paid more than the standard rate.
D) determine the total cost of labor for production

Correct Answer: