Multiple Choice
The variable overhead efficiency variance is calculated as
A) actual cost − (actual quantity × standard price) .
B) actual cost − (standard quantity × standard price) .
C) standard price × (actual quantity × standard quantity) .
D) actual results minus flexible budget amount.