Multiple Choice
All of the following are required elements in a purchase requisition except _____.
A) quantity and date required
B) estimated unit cost
C) operating account to be charged
D) authorized signature
E) identification and approval of a supplier by the end user
Correct Answer:

Verified
Correct Answer:
Verified
Q5: Contract management should be used to trigger
Q6: _ is the process of using unit
Q7: Suppliers are more often being paid through
Q8: The authority to review and challenge specifications
Q9: The _ helps protect the carrier against
Q11: The purchasing cycle begins with the _.<br>A)selection
Q12: Almost all firms establish blanket purchase orders
Q13: All of the following are conditions under
Q14: When a situation arises when an internal
Q15: _ is the process of collecting historical