In Construction Contracts, Penalty Clauses Are Technically Called "Liquidated Damages

Question 42

True/False

In construction contracts, penalty clauses are technically called "liquidated damages clauses;" if they are labeled "penalty" clauses, there is a long line of cases that says they are not enforceable.