    In a PERT Network, A/an _____ Is the Latest Point
Solved

In a PERT Network, A/an _____ Is the Latest Point

Question 18

Question 18

Multiple Choice

In a PERT network, a/an _____ is the latest point in time an activity can begin without delaying the entire project.


A) late start
B) late finish
C) early start
D) early finish
E) on time finish

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q13: Value analysis traditionally applies to tangible products,

Q14: Which of the following is not one

Q15: The primary objective of value analysis is

Q16: In a PERT network, the difference between

Q17: In a PERT network, the difference between

Q19: Which of the following is not one

Q20: When referring to learning improvement, the _

Q21: _ actions and resources are those actions

Q22: Because so few processes move across functional

Q23: _ actions and resources are those that

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines