Multiple Choice
What is the term given to the kanban used to signal to a previous stage that material can be withdrawn from inventory and transferred to a specific destination?
A) Customer kanban
B) Production kanban
C) Move or conveyance kanban
D) Vendor kanban
Correct Answer:

Verified
Correct Answer:
Verified
Q24: JIT type approaches have many different names.
Q25: Kanban is sometimes called the:<br>A) Invisible conveyor<br>B)
Q26: Which of the following is NOT a
Q27: The just-in-time approach assumes that each stage
Q28: Which of the following basic working practices
Q30: Depending on the type of kanban being
Q31: Producing goods and services exactly when they
Q32: The 'lean' concept has much wider implications
Q33: Which of the following is NOT a
Q34: Which of the following methods is NOT