On a Day-To-Day Basis, Works Orders Intended to Be Issued

Question 20

Multiple Choice

On a day-to-day basis, works orders intended to be issued from the MRP will often have a variable effect on the loading of particular machines or individual workers. Which plans project
This load ahead?


A) Organisational work plans
B) Rough cut capacity plans
C) Capacity requirements plans
D) Resource requirements plans