During 2022 Cotte Manufacturing Expected Job No

Question 56

Multiple Choice

During 2022 Cotte Manufacturing expected Job No.59 to cost $300000 of overhead $500000 of materials and $200000 in labor.Cotte applied overhead based on direct labor cost.Actual production required an overhead cost of $295000 $570000 in materials used and $220000 in labor.All of the goods were completed.How much is the amount of over- or underapplied overhead for this job?


A) $5000 underapplied
B) $5000 overapplied
C) $35000 underapplied
D) $35000 overapplied

Correct Answer:

verifed

Verified