Multiple Choice
Which of the following sources would most likely be responsible for persistent "project cost over-runs"?
A) rapidly rising inflation
B) delays in obtaining contracts and permits
C) lack of raw materials
D) forecasting bias by the sponsoring manager
Correct Answer:

Verified
Correct Answer:
Verified