Multiple Choice
If the IRR for a project is 15 percent, then the Project's NPV would be:
A) negative at a discount rate of 10 percent.
B) positive at a discount rate of 20 percent.
C) negative at a discount rate of 20 percent.
D) positive at a discount rate of 15 percent.