Multiple Choice
Which of the following would not be included in a risk management plan (RMP) in relation to a specific risk?
A) What the organisation is doing to enhance the risk
B) What the organisation is doing to remove the risk
C) What the organisation is doing to control the risk
D) The level of loss an organisation is prepared to accept from the risk
E) Contingency plans to be put in place should the risk occur
Correct Answer:

Verified
Correct Answer:
Verified