Which of the following shows the correct order of a risk management process?
A) Identify, evaluate, analyse, treat
B) Identify, analyse, evaluate, treat
C) Identify, analyse, treat, evaluate
D) Identify, treat, analyse, evaluate
E) Identify, evaluate, treat, analyse
Correct Answer: