Which of the following strategies would not be appropriate to deal with an identified risk to a project?
A) Prevent it.
B) Mitigate it.
C) Accept it and hope the consequences will be minimal.
D) Accept it and plan how best to live with it.
E) Transfer it to another party (e.g. a contractor or insurance company) .