A network diagram:


A) helps to identify the minimum amount of time needed to complete a plan or project.
B) allows a planner to identify which tasks can be delayed should there be a need to shift resources to catch up on other tasks.
C) may utilise critical path analysis (CPA) to illustrate how various activities relate to each other.
D) allows a planner to schedule, manage and monitor a plan's tasks.
E) All of these responses are correct.