The First Step in the Development of a PERT Chart

Question 50

Multiple Choice

The first step in the development of a PERT chart is


A) assigning an estimated cost to each task.
B) analyzing the tasks and determining the sequence in which they must be performed.
C) estimating the time needed to complete each task.
D) identifying the probabilities that each step in the project can be successfully completed without exceeding the estimated cost.