Multiple Choice
Review the PERT Network below: If it takes 1, 2, or 3 weeks for each activity (represented by a box) to be completed, the critical path is represented by:
A) the path that begins with "Start" and continues with all boxes labeled with No. 1.
B) the path that begins with "Start," continues with all boxes labeled with No. 2, and concludes with "Finish."
C) the path that begins with "Start," continues with one box labeled with No. 2, proceeds with all boxes labeled with No. 3, and concludes with "Finish."
D) the path that begins with "Start," continues with all boxes labeled with No. 1, and concludes with "Finish."
Correct Answer:

Verified
Correct Answer:
Verified
Q37: In manufacturing, one way to compete with
Q38: _ is the creation of goods and
Q39: In _, materials are physically or chemically
Q40: Quality control is a continual process of
Q41: _ is the physical arrangement of resources
Q43: A(n) _ puts together components to make
Q44: Today, due to technological advancements, manufacturers in
Q45: American manufacturers have emphasized continuous improvement as
Q46: When it comes to location decisions, labor
Q47: Facility location is the process of selecting