Solved

Sparky Knows That Installing the New Equipment and Training Workers

Question 225

Multiple Choice

Sparky knows that installing the new equipment and training workers to use it efficiently will be a long and complex process consisting of many different tasks. Which of the following methods would help him determine how long this project is likely to take?


A) TPSM (task priority scheduling method)
B) DA (dependency analysis)
C) TRSS (task and resource scheduling system)
D) PERT (program evaluation and review technique)

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge