Multiple Choice
The purpose of determining the critical path on a PERT network is to
A) identify the sequence of tasks that takes the longest to complete.
B) estimate a payment schedule so that a budget can be established.
C) find the sequence of events that is the most expensive to complete.
D) establish a delivery schedule for a just-in-time inventory control program.
Correct Answer:

Verified
Correct Answer:
Verified