Multiple Choice
In order to schedule deliveries,Minimotors's suppliers need detailed information about when parts are needed.Minimotors will purchase a sophisticated computer application that will link its operation to sales forecasts to make sure needed parts and supplies are available at the right time to meet customer demands.This planning system is known as:
A) Materials requirement planning MRP) .
B) Program evaluation and review technique PERT) .
C) Minimum daily requirements scheduling MDRS) .
D) Sales-based requirements forecasting SBRF) .
Correct Answer:

Verified
Correct Answer:
Verified
Q55: Computers and robots are only useful in
Q100: Mini-Case<br>"These are exciting times for our company.
Q123: Which of the following statements best reflects
Q137: The purpose of determining the critical path
Q226: Justin is a project manager for a
Q237: Contemporary producers and their suppliers<br>A) locate in
Q240: Companies such as IBM prefer to stay
Q248: Enterprise resource planning (ERP) goes beyond the
Q272: An important strategy in operations management is
Q312: Justin Tyme is a manager at Elastic