Multiple Choice
COGNITIVE ASSESSMENT What occurs during scope creep?
A) one bad programming decision leads to another and work must be undone
B) the project manager decides to remove certain planned activities in order to save time
C) one activity leads to another that was not originally planned
D) feasibility of the project is reevaluated
Correct Answer:

Verified
Correct Answer:
Verified