Multiple Choice
Architect LLC enters into a contract with Barn & Silo Inc. to provide designs for a certain number of farm buildings. Architect provides fewer than half of the designs by the time specified in the contract because the firm is busy with other projects. Architect's performance is most likely
A) a material breach.
B) a minor breach.
C) a reasonable breach.
D) no breach.
Correct Answer:

Verified
Correct Answer: