Multiple Choice
Restore Inc. contracts to resurface the pools at Swim Park by June 1. Restore knows that if performance is not timely, Swim Park will have to delay its seasonal opening. Restore finishes the job June 15. In a suit for breach, Swim Park can recover
A) the cost of new pools.
B) the difference between the contract and market prices for the work.
C) the loss of profit from the delayed opening.
D) nothing-the work is done.