A band joist, or ____, is bolted to poles when constructing pole buildings.


A) foundation
B) wracking
C) sheathing
D) header

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q16: When installing nonmetallic-sheathed cable through wood wall

Q17: Pole buildings are a variation of _

Q18: In both platform-frame and balloon-frame construction, the

Q19: Post-and-beam framing uses _.<br>A) closely spaced members<br>B)

Q20: Diagonal braces can be attached to the

Q21: Post-and-beam framing is _.<br>A) never left exposed<br>B)

Q22: When wall framing is done with 2

Q23: Poles, which are treated to be insect

Q25: Wall _ are the main framing members

Q26: The advantages of structural integrated panels (SIPs)

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines