Paul, a Contractor, Has a Contract to Build a New

Question 71

Multiple Choice

Paul, a contractor, has a contract to build a new office building for Bill. The contract contains a provision requiring Paul to furnish a certificate of occupancy from the building inspector before Bill is required to pay. This provision is:


A) an express condition.
B) an implied-in-fact condition.
C) an implied-in-law condition.
D) a condition subsequent.

Correct Answer: