Paul, a contractor, has a contract to build a new office building for Bill.The contract contains a provision requiring Paul to furnish a certificate of occupancy from the building inspector before Bill is required to pay.This provision is:
A) an implied-in-fact condition.
B) an implied-in-law condition.
C) an express condition.
D) a condition subsequent.
Correct Answer:

Verified
Correct Answer:
Verified