Multiple Choice
Perry is building his house and orders a hot water heater from Jones Co.to be installed by them.The hot water heater they sent has a 45-gallon capacity, but Perry had ordered a 60-gallon capacity.Jones cannot provide a 60-gallon heater for two months, so Perry cancels the contract and gets a heater from another company.Jones Co.says it must be allowed to install the replacement heater.What result?
A) Jones wins; Perry can only cancel if installation is also delayed two months.
B) Perry can cancel the whole contract, but he is then limited in his recovery of damages.
C) Perry wins since the contract breach concerns the whole contract.
D) Jones wins; Perry can only cancel the portion of the contract regarding the goods.
Correct Answer:

Verified
Correct Answer:
Verified
Q6: A contractual remedy is optional unless the
Q10: In what three situations will a seller
Q19: If the buyer is insolvent and has
Q27: If the buyer makes a wrongful rejection,
Q38: Under the CISG, what are the damages
Q48: One hundred porch swings have been identified
Q49: A seller's remedies upon the buyer's default:<br>A)
Q52: The fair market value of a 10-foot
Q52: MoVu Co. contracted to buy 400 round plastic
Q56: On February 21, Cara wrote to Pandora