Question 50

Multiple Choice

Soft Chair Company contracts to deliver one hundred chairs to Stuffy Furnishings Store on May 1. Soft tells Stuffy on April 15 that delivery will be delayed until June 1. Stuffy


A) may await performance, sue Soft, or suspend its own performance.
B) must await Soft's performance for a commercially reasonable time.
C) must immediately sue Soft for breach of contract.
D) must give Soft thirty days to change its mind and correct the problem.

Correct Answer: