    The ____ Is an Allowance for the Extra Material Required
Solved

The ____ Is an Allowance for the Extra Material Required

Question 12

Question 12

Multiple Choice

The ____ is an allowance for the extra material required to fill volumes with compacted material rather than loose material.


A) growth factor
B) stability factor
C) compaction factor
D) compression factor

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q7: A large-size excavation company is generally equipped

Q8: The cost of transporting equipment includes the

Q9: Excavation contractors tend to concentrate on a

Q10: Material prices for backfill have three main

Q11: Perhaps the most important job factors that

Q13: When soil or gravel is excavated, the

Q14: Which of the following types of excavation

Q15: Whenever it is possible, the contractor will

Q16: Transportation of major items of equipment-backhoes, bulldozers,

Q17: In order to determine the labor price

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines