    With the ____ Method of Estimating, a Certain Unit That
Solved

With the ____ Method of Estimating, a Certain Unit That

Question 2

Question 2

Multiple Choice

With the ____ method of estimating, a certain unit that is common to all projects of this type is selected and the number of these units is calculated for each project.


A) price per unit
B) single-rate
C) piece
D) job

Correct Answer:

verifed

Verified

Related Questions

Q1: The _ estimating method can be used

Q3: _ estimation methods include price per typical

Q4: The _ of the building is calculated

Q5: The assembly method of estimating is less

Q6: The_ method is the most sophisticated preliminary

Q7: Using the _ method, a building, which

Q8: Which of the following is NOT a

Q9: _ is the most common method of

Q10: Using the price per unit estimating method

Q11: _ estimating methods include the price per

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines