    Exam 16: Budget Estimating
  5. Question
    Single-Rate Methods of Preliminary Estimating Include All of the Following
Solved

Single-Rate Methods of Preliminary Estimating Include All of the Following

Question 14

Question 14

Multiple Choice

Single-rate methods of preliminary estimating include all of the following EXCEPT ____________.


A) cost per unit
B) cost per unit area
C) cost per typical bay
D) cost per unit volume

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q9: _ is the most common method of

Q10: Using the price per unit estimating method

Q11: _ estimating methods include the price per

Q12: The _ is defined as the area

Q13: Estimators typically turn to preliminary estimating methods

Q15: Assembly estimating can be a powerful cost

Q16: Composite unit prices that are custom made

Q17: Typical bay estimates are very common because

Q18: The typical bay method is more flexible

Q19: Single-rate methods are generally accurate and can

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines