Multiple Choice
The ____ contingency is an amount that is added to the cost estimate which reflects the price increases that are anticipated over the time between the date of the analysis being used and the time when the new project is constructed.
A) overage
B) escalation
C) satisfaction
D) appreciation
Correct Answer:

Verified