Multiple Choice
A method of handling the problem of review questions is to compile a list of all the questions that arise, the ____, then later send a single e-mail to the prime consultant to deal with all the items that have accumulated.
A) punch list
B) query register
C) query list
D) risk register
Correct Answer:

Verified
Correct Answer: