True/False
Deduct for openings in the concrete that are less than one cubic foot (0.05 cubic meters)of volume.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q4: Linear inserts such as waterstops are measured
Q5: Welded wire mesh shall be measured in
Q6: Concrete shall be measured in _ net
Q7: Vertical finishes are measured in _ of
Q8: Because the concrete is detailed on the
Q10: Because only the _ of formwork is
Q11: Grout to anchor bolts and base plates
Q12: The estimator measures the surface area of
Q13: Concrete is classified in terms of the
Q14: Saw cuts for concrete are measured in