Under CISG,all of the following are requirements to excuse nonperformance of a contract except:
A) an impediment is beyond a party's control.
B) an impediment was not reasonably foreseeable at the time contract was concluded.
C) notice of the impediment was given to the other party.
D) the impediment is of such a monetary value as to shock the conscience.