Multiple Choice
A DRP system is usually coupled with a _____ system in an attempt to manage the flow and timing of both inbound materials and outbound finished goods.
A) Kanban
B) VMI/consignment
C) MRP
D) JIT
Correct Answer:

Verified
Correct Answer:
Verified