In the SDLC, the First Major Task for an Assembled

Question 73

Multiple Choice

In the SDLC, the first major task for an assembled project team is to ________.


A) design system components
B) assess the project's feasibility
C) plan the project
D) define system goals and scope

Correct Answer: