Multiple Choice
What are the two major groups of the MasterFormat system?
A) Procurement and Contract Requirements and Specification groups
B) Process Equipment and Facility Services
C) Site and Infrastructure
D) General requirements and Facility Construction
Correct Answer:

Verified
Correct Answer:
Verified
Q5: Closed specifications are often used on renovations
Q6: The descriptive specifications are _.<br>A) exclusively used
Q7: Specifications describe which of the following?<br>A) site
Q8: What is one of the major categories
Q9: The Description of Materials form consists of
Q10: The written specifications constitute the bulk of
Q11: A minimum standard for quality or performance
Q12: Which section of the specifications describes the
Q14: What should drawings do?<br>A) show the types
Q15: A construction document should be limited to